Construction Delivery Methods Head to Head: CMAR vs. Design-Build

By 

Last Updated Nov 22, 2023

Construction contractors discuss terms of different project delivery types .

Project delivery methods dictate the roles and responsibilities of project stakeholders throughout the design and construction of a new build. Which method owners choose depends on many factors, including the owner’s skillset and comfort level with the building process, and the specifics of the project at hand. 

Two popular project delivery structures, design-build and construction manager at risk, offer benefits and challenges to the stakeholders on a construction project, and there’s a number of factors owners must consider when selecting one for their projects.  

Owners should evaluate their own skills, abilities, and willingness to be heavily involved, and the risks they’re okay with shouldering.

 In this article, we'll examine the two popular methods, and help owners choose which might work for their next project.

Table of contents

Understanding Construction Manager at Risk (CMAR)

The CMAR method is sometimes referred to as CM/GC, because it effectively combines the construction manager and general contractor into a single role.

When using CMAR, the owner contracts a design firm to help begin the design process for a new project. Soon after the the design process begins, the owner brings in the construction manager to consult on the design plans. This early collaboration presents benefits for both the owner and construction manager.

The owner gets added expertise from an experienced pair of eyes. Together, the owner, designer, and construction manager can eliminate many design errors, optimize the project schedule, and balance the owner's wishes and desires with the desired budget and timeline.

Meanwhile, the contractor gets to spend time with the design to fully understand all of its elements, the site makeup, and other conditions that could impact construction.

Once the design is complete, the owner puts it out for bids. The CM who consulted on the project is not necessarily the one who wins the bid; however, additional time with the design (which could lead to a more competitive bid) and history with the owner does make it more likely that the consulting CM will go on to complete the build.

The owner and the CM then enter into a contract to build the project. The contract will often set out a guaranteed maximum price (GMP) for the owner, which takes much of the risk from the owner and places it onto the construction manager.

CMAR projects may be split into multiple phases, so construction can begin on one phase even before the design of the next phase is complete. In this way, CMAR can reduce project timelines compared with the traditional DBB method.

Project Management

On budget, on schedule, and in control.

Build with less risk and bigger profits.

Request a Demo
Illustration of construction worker looking at charts on giant tablet

The Benefits of CMAR

While relatively new, CMAR has become quite popular for owners for a number of reasons. Below are some of the factors that make this project delivery structure a favorable choice. 

Added input to construction design

CMAR allows contractors to get a concentrated early look at, and influence, over construction designs. The added expertise a CM brings to the design process can help avoid some challenges and change orders during construction, and even result in a better quality build.

Bidding advantages

CMAR allows contractors to get more time and in-depth knowledge of the design, which can inform a more specific and possibly more competitive bid. A better bid means more potential savings for the owner and better chances of winning the project for the contractor.

Cost certainty for the owner

Because construction managers provide a GMP to owners in the contract in the construction documents, owners may benefit from a lowered financial risk level if the project costs go over budget. 

The Cons of CMAR

Contractors are pushing for wider use of the CMAR method because of the added input they get into design and the edge they get in bidding a project. However, there are also downsides the CM must consider when joining this type of project method. 

Greater risk for the CM during construction

The construction manager on a CMAR project takes on a great deal of risk. The guaranteed price leaves the CM on the hook for any extra costs resulting from surprise site conditions, materials procurement delays, or regulatory changes that necessitate a late change in design.

Prolonged construction timeline

If the owner has split the project into multiple phases, CMAR may offer the CM the opportunity to overlap design and construction to save some time. But the sequential timeline CMAR projects follow can't compete with the time savings the DB method offers.

Understanding Design-Build

The design-build delivery method has been around for a long time, and thanks to its collaborative nature and ability to deliver projects with a highly compacted schedule it’s experiencing a resurgence in certain regions. Nearly half of all projects in the US are now delivered using the design-build delivery method.

An owner who chooses design-build will begin project conception, feasibility, and site selection in consultation with a design-build team. Once a project design and cost estimation has begun, the owner will issue a request for proposal (RFP), often only sending it out to select proposers.

With CMAR, the owner selects a design-build team based on both the project quote and the value that the design-build team can offer to the project. 

The design-build firm the owner hires will then take over and complete the design process, and firm up the work's scope, schedule, and budget. Then, throughout the construction phase, the design-builder will handle all subcontracting, materials procurement, daily project management, and owner communications.

Design-build has two benefits for owners willing to loosen their grip on the project reins: it gives the owner a single point of contact, reducing the owner's administrative burden through project completion, and offers the potential for faster project completion.

The Benefits of DBB

Much like CMAR, design-build brings project stakeholders together earlier than other project methods. However, DBB organizes roles and responsibilities differently to offer unique features and downsides.

A compacted schedule

One of the best-celebrated features of design-build is its ability to deliver projects in a much shorter time frame compared with many other models. Because the design-build team is a single unit, it can begin construction on parts of the project even while design efforts for later phases are ongoing. Pulling double-duty can allow the DB team to shrink a project schedule from two decades to just five years.

Increased collaboration

The general contractor in charge of construction by the DB method is involved right from the beginning. The contractor can lend expertise and experience to the design process that could contribute to fewer problems during construction, and even a more efficient and cost-effective build overall.

Lower owner risk

Because the design-build team has the project right from the starting line, it accepts much of the risk for both the design and construction phases. Any extra costs fall to the design-builder, whether from rework due to design flaws, construction delays, or any other unexpected issue. The owner also has a single point of contact from whom to get project updates.

Disadvantages of Design-Build

The DB method can be a great option for owners looking to streamline and simplify the project process. Potential downsides have a lot to do with communication between project stakeholders.

Owners have less control

Owners who choose the DB method remain involved throughout the project but are no longer the conduit of information between other project stakeholders.

Further, owners have less transparency into individual project costs when they price out a combined DB team, compared with pricing design and construction individually.

Increased risk for the DB team

The other side of the coin is that DB substantially increases risk for the design-build team. The level of this risk depends on the level of cooperation and collaboration between designers and builders within the team.

The design-build team can be made up of the owner's selection of architect, engineer, and contractor, who will then become a unified design-build entity, or the owner may choose a single firm that chooses its own partnering members.

Regardless of the owner's selection process, the team bands together to become responsible for project delivery. If the firms are well-matched, the project experiences all the potential benefits of DB, but if collaboration is lacking and the construction team takes issue with the designs, those risks can become elevated.

Similarities between CMAR and Design-Build

The CMAR and DB project delivery methods have a few things in common:

  • They both involve getting the contractor involved early in the design process
  • That early involvement can improve design and reduce changes in design once construction has begun
  • They may both involve some design and construction overlap, though DB has the best chance of significant schedule compression

The owner in a DB project must be comfortable handing over a project and releasing both risk and input over to the design-build team. Design-build excels at delivering complex builds with a reduced timeline. Completing the design on large and complicated projects can be a long and arduous process – DB allows construction to begin while designers hammer out later phases.

The CMAR construction delivery method will be a better fit for owners who wish for more control over a project's design. While owners often wonder whether CMAR will lead to overpriced bids because of the transferred risk to the CM, the broader and deeper knowledge the CM has of the project's design can actually lead to more precise bidding and lower costs.

In the end, the decision between CMAR and DB methods comes down to the owner's comfort level with managing a project, and the desired timeline for the project's completion.

this is part of the series

Project Delivery Methods

Currently Reading

Construction Delivery Methods Head to Head: CMAR vs. Design-Build

1 of 1

Categories:

Project Execution

Written by

Alex Six

Alex Six is a Mid-Market & Majors Civil & Infrastructure Overlay Account Executive for Procore. Alex has a long background in the construction industry beginning with an internship with one of the biggest contractors in the world, and expanding across projects with teams as small as 4 people and as large as multi-billion dollar budgets with large teams and disciplines. His resume includes Caltrans highways & bridges, Metro light rail & underground, as well as airport runways and utilities.

View profile

Kristen Frisa

17 articles

Kristen Frisa is a freelance writer specializing in finance and construction technology. She has helped numerous companies to provide value to their readers and establish their expertise in their industries. Kristen holds a degree in philosophy and history and a post-graduate certificate in journalism. She lives in Ontario, Canada.

View profile
Win More Work

Get discovered for relevant work on the Procore Construction Network.

Get a Free Account
Construction professionals

Explore more helpful resources

article-image

Time and Materials vs. Fixed Fee Contracts: Pros, Cons & Choosing the Right Fit

In construction, managing projects efficiently while also ensuring financial stability is a delicate balance. Project owners are searching for the best quality work, performed in the shortest amount of time,...

article-image

Successfully Navigating Public-Private Partnerships in Construction

A Public-Private Partnership (PPP or P3) is a contractual agreement that sees government agencies and private companies working together to build major infrastructure projects. Public-private partnerships allow governments to tap...

article-image

Successfully Navigating Change Management in Construction

Change management in construction refers to any alteration to the original scope of work after the project has commenced. Whether the changes are simple or complex, they often affect a...

article-image

Multi-Prime Contracts: Understanding the CMMP Method of Project Delivery

Construction projects often involve a sole owner that’s in charge of everything from finances to project progress to design, and use a sole prime contract for all the building work....

Procore is committed to advancing the construction industry by improving the lives of people working in construction, driving technology innovation, and building a global community of groundbreakers. Our connected global construction platform unites all stakeholders on a project with unlimited access to support and a business model designed for the construction industry.

LinkedIn Icon
LinkedIn
Facebook icon
Facebook
Twitter icon
Twitter
Instagram Icon
Instagram
YouTube icon
YouTube

Call us at (844) 692-0626 to speak with a product expert.

Apple LogoApple App StoreGoogle Play logoGoogle Play

Downloads

Apple LogoApple App StoreGoogle Play logoGoogle Play
  • Privacy Notice
  • Terms of Service
  • Do Not Sell Personal Information

© 2024 Procore Technologies, Inc.